July 2018 Update:

TxDOT has completed the redesign of certain underground piping systems to avoid existing utilities that were found to be in conflict. TxDOT did this to expedite the work since getting the existing utilities to move their lines would take longer than redesigning their systems where possible. Many thanks to TxDOT for this.

CoServ gas has completed moving portions of their lines that TxDOT could not avoid. Ed Bell construction is moving full steam ahead to complete the road project now that all the underground conflicts have been eliminated. TxDOT hopes to complete the remaining lanes and drives for a traffic switch onto the new lanes in October.

Event calendar

 

November 2018
S M T W T F S
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 1